Building Melbourne’s Northern Sustainable Supply Hub

August 31, 2026

Alex Fraser’s Northern Sustainable Supply Hub has spent the past five years transforming from a former quarry with a temporary plant into an integrated recycling and asphalt supply hub for Melbourne’s northern growth corridor.

The 35-hectare site sits between inner-urban redevelopment and the outer growth areas, with excellent Hume Freeway access and around a million tonnes of raw feed storage.

The asphalt manufacturing plant with capacity to process up to 70% recycled content was commissioned in 2022.

Alex Fraser Managing Director Peter Murphy says Epping’s $40 million transformation is about creating a high capacity, integrated sustainable construction materials supply hub.

“Our vision for Epping has always been to build a modern, integrated supply hub. The hub can recover more local materials and turn them into the high-quality products Melbourne’s north needs, well into the future.”

The site’s development has followed a deliberate sequence.  An asphalt manufacturing plant running at 240tph with capacity to process up to 70% recycled content was commissioned in 2022, servicing the North-East Link project and the northern suburbs’ residential, commercial and industrial subdivisions.

In 2024, Epping Recycling commissioned its Rock Circuit, with annual capacity of 300kt.

In 2024, a three-stage crushing system to efficiently process local basalt rock into 20mm roadbase was commissioned.

This July, a new Recycling Circuit was commissioned. The Recycling Circuit replaces a ageing, modular plant that could no longer meet market demand. The new circuit handles concrete and C&D material through a separate primary circuit integrated with the existing rock plant, lifting output to nearly double the previous capability.

Next up, is a $2m investment in robotics, scheduled for 2027

The engineering reflects the realities of C&D materials rather than virgin quarry rock.  In particular the challenge of separating large amounts of steel while being relentless about production efficiency has been an ongoing focus.  The plant is built ready for parent company Heidelberg Materials Australia’s Aggregates Remote Optimisation Centre (AROC) integration.

Truck turnaround time is critical in our industry and recent site reconfiguration has improved haul road layout so that customer trucks can get on and off the site very efficiently.  The site also operates a high capacity blend plant to support large hourly tonnages of cement treated road base to major projects.

Next up, is an investment in robotics, already in motion and scheduled for 2027 execution.

Over the past five years, Epping has been rebuilt into an integrated asphalt and recycling hub.

Murphy says, “The next phase is about using automation to help our team with the  repetitive work while improving the consistency and reliability of the plant. It’s a practical investment in safety, productivity and the long-term capability of the site.”

Over the past five years, Epping has been upgraded stage by stage into an integrated asphalt and recycling hub, with each investment enabling the next. By recovering concrete, brick, asphalt and rock from local construction and demolition projects, the hub keeps valuable resources in circulation and returns them to the market as lower-carbon construction materials for new infrastructure.